Foundation excavation completed – NetZeroBuild update

by

Progress Update: July 24-2013

NetZeroBuild Progress Report

1.We have all the main beams cut and ready to install.
2. We did the excavation today and it went perfect.
3. The first few support trees have had the white oak inserts installed

So we are off to the races ..next is:

1. Keep working on the trees
2. Get footing forms in and poured
3. Prep all the trees for install